1 carefully check the machine parts are connected firmly;
2 according to the requirements of the manual lubrication;
3 no-load test 3 ~ 2 hours
4 if the above steps have not found the problem, then open the elevator and the spiral conveyer, the new projectile door from the cleaning room to add about 600Kg to the equipment. The projectile by the conveying screw conveyor and lift hopper, finally stored in the lower part of the separator. After driving, the projectile will flow through the electric valve for the pill blasting machine at the lower part of the hopper, the clean indoor cleaning work for blast cleaning.
5 in the regulation of shot blasting machine, shot blasting machine set should pay attention to the directional position should enable the projectile ejection full coverage in cleaning a workpiece, otherwise it will affect the efficiency of cleaning. The window directional set position, can refer to Fig. five for installation position, when necessary in a piece of wood coated with black ink or a piece of paper, placed by cleaning workpiece position, start blasting, artificial to shot blaster tube with a small amount of the projectile, check the projectile with the position, such as ejection position is not correct, should adjust the orientation set, in order to obtain the ideal location for. Directional set and adjusted, it can make the load test, after 30 minutes after adding 400Kg projectile shot.
|